Shard Place Project

Installation of kitchen supply and extract ductwork at St Thomas Street, London. FSL overcame post-contract challenges and site access constraints to deliver on time, working closely with Borough Engineering and MACE. Recognised for speed, adaptability, and quality workmanship.

Client

Client- Borough Engineering Services Ltd
Location
St Thomas Street, London SE1

Services

Kitchen Extract EN120, EN121 (Both EN1366-1)
Kitchen Supply EN105 (EN1366-1), GSS DW155 Class B

Overview

nstallation of the new retail kitchen supply & extract ductwork was challenging because these were new systems added after completion of the original contract. 

FSL worked closely with Borough/MACE to identify the best routes for the new ductwork and with the process of identifying and re-locating of other services to create the required space.

Access to install was another challenge because access to the soffit using standard access equipment was not possible. FSL again worked with Borough/MACE to solve access issues to difficult areas.

FSL were praised by the client throughout the contract for expediating ductwork through the factory. The site engineers also got special mention due to the effort & hours they put in to complete all areas before programme completion dates, which were extremely tight. FSL were also praised for the extremely high standard of workmanship.

FSL were employed to carry out post contract works on other base build ductwork systems, due to the excellent relationship built with the client during the works. 